Project overview

The project comprised the electrical installation and upgrade of two egg incubation systems, the automated feeder systems serving the tank hall, and containment, distribution and prewire upgrades across four tank hall rows. The scope covered general lighting and power throughout, comprehensive industrial cable tray containment and steel wire armour (SWA) installation and dressing, prewire of control wiring and the dissolved-oxygen monitoring system, and final commissioning and testing — all planned and sequenced by Brian Stevenson Ltd to meet production deadlines for the start of farm operations. The work was carried out in direct, ongoing technical partnership with the client’s engineering team and on-site management throughout, rather than to a fixed drawing package handed down in isolation.

Compliance & safety

  • CITB SMSTS lead Zero lost-time-incident safety record
  • Live-production sequencing Upgrades staged around an operating tank hall with no loss of production capacity
  • Multi-trade audit Complete site log verification
  • BS 7671:2018 (2022) Verified electrical compliance, with recorded loop-impedance and prospective-fault-current test data per circuit
Request certification records

Delivery & engineering scope

01

Programme Sequencing & Site Control

Works planned and sequenced row by row around a live tank hall, keeping each system available to production while the next was taken offline for upgrade.

02

Egg Incubation Systems

Electrical installation across two egg incubation systems, including associated control and power connections.

03

Automated Feeder Systems

Installation of feeder control boxes, isolators and a dedicated feeder PLC distribution board, with power and control prewire to each feeder unit across the tank hall.

04

Tank Row Upgrades

Containment, distribution and power upgrades delivered to the first pair of tank hall rows, including feeder control tray and cabling.

05

Additional Row Installation

Containment, earth bonding and distribution board installation across a further pair of tank hall rows.

06

Cable Containment & SWA Installation

Comprehensive industrial cable tray containment throughout the tank hall, with steel wire armoured cable installation and dressing to all rows and plant areas.

07

General Lighting & Power

Full lighting and power installation across the tank hall, including high-level, walkway and emergency lighting circuits.

08

Control & Monitoring Prewire

Prewire of control wiring and the dissolved-oxygen monitoring system, integrated into the wider plant control network.

09

Commissioning & Handover

Circuit-by-circuit testing and energisation, with the full installation commissioned and handed over in alignment with production deadlines ahead of the start of farm operations.

Collaboration to deliver

The upgrade was run as a three-way technical partnership rather than a standard design-and-install contract: the client’s engineering team, the client’s on-site management, and Brian Stevenson Ltd’s own site team worked jointly through load calculations and installation sequencing as each system and row was upgraded. That close, continuous technical dialogue — carried through to final commissioning and testing against a fixed production deadline — was what allowed the entire tank-hall installation to be delivered without rework or capacity surprises at energisation.

Related case study

Principal site management and multi-trade delivery on a freshwater broodstock hatchery in the North West Highlands, with fish life-support control wiring delivered in-house.

View broodstock hatchery case study